  • CONSTRUCTION PROGRESS UPDATE

    3 August 2020

    Stage 2 concrete structure is now at Level 14.

    Aqualand's in-house construction team are progressing well with the following key construction milestones:
     

    • Stage 2 concrete structure is now at Level 14
    • Structural steel to slab extensions are now completed
    • High Level services roughin are well underway throughout the building
    • Façade installation has commenced with the northern balcony slider framing underway
    • Internal partition framing has commenced

     
    In the next quarter update you will see the following construction milestones achieved: 
     

    • Topping out of the concrete structure
    • Commencement of the curtain wall façade
    • Commencement of the luxury internal finishes
    • Commencement of the kitchen installation

     
    Despite the recent COVID 19 restrictions, we still remain on-track with our construction programme comprising a targeted date for commencing settlements in Q1, 2021.