  • CONSTRUCTION PROGRESS UPDATE

    13 July 2019

    MILESTONE ACHIEVED: In June 2019 Aqualand completed the Stage 1 Demolition of the existing structure, making way for the new lift and stair core construction to progress unimpeded.

    • New lift and stair core has been poured to level 4.
    • Existing precast façade panels have been safely removed down to level 3. 
    • Scaffolding has been safely removed down to level 3 on the northern, eastern, and southern elevations.
    • South Eastern corner demolition works will commence in July 2019 and will commence construction of the new slabs in August 2019.
    • Stage 2 demolition (removal of the existing cores) is expected to commence in October 2019.