CONSTRUCTION PROGRESS UPDATE
15 August 2018
Catch up on the latest news on the construction of Blue at Lavender Bay.
- A-class perimeter hoarding installation is completed. Photo above shows the final stages of A-class hoarding installation in mid July.
- The new Blue sales suite construction at 118 Alfred St is completed. The sales suite is officially open for business.
- Early works tender is underway with site commencement being targeted in October 2018.
- Investigative survey & exploratory works are being undertaken in September 2018, these works should be done within a week.