  • CONSTRUCTION PROGRESS UPDATE

    13 September 2019

    Stage 2 Demolition of the existing core commences on the week commencing 23 September 2019.

    Aqualand are due to commence Stage 2 Demolition of the existing concrete core on the week commencing 23 September 2019.  Aqualand anticipate that Stage 2 demolition will continue until circa March-April 2020.  The following demolition works will be undertaken during this time:

     

    • Removal of the existing concrete core, located to the western elevation of the 61 Lavender St building, from top level down.
    • Progressive dismantle of the scaffolding on the western elevation of the building.
    • Removal of the existing precast concrete spandrel panel on the building’s western elevation.

     

    We are also due to commence demolition of the basement 3 slabs on 18 September 2019.  Sustained noise from jackhammering and saw cutting emanating from the basement levels are to be expected within the initial 1-2 weeks period.  This will be followed by intermittent noisy works in the basements throughout the Stage 2 demolition phase.

     

    All demolition works will be undertaken within the approved DA hours.