  • CONSTRUCTION PROGRESS UPDATE

    24 January 2019

    Catch up on the latest news on the construction of Blue at Lavender Bay.

    • Tower crane was installed prior to Christmas 2018 and is now in operation.
    • Perimeter hoardings have been erected around the construction site.
    • Stage 1 (friable) asbestos clearance certificates received for 80% of the building.
    • Basement excavations are underway.
    • Removal of existing precast façade spandrels have commenced.
    • Demolition works are progressing with the removal of the existing upper level slabs.