  • CONSTRUCTION PROGRESS UPDATE

    19 December 2019

    Stage 2 Demolition of the existing core is well underway and on track to complete by March-April 2020.

    Aqualand’s in-house construction team has completed the following key construction milestones prior to the year's end:

     

    • Construction of the new stair and lift core is now complete with the new core lobby slabs and stairs poured to Level 18;
    • Stage 2 demolition commenced in September, which is currently down to Level 8.  We anticipate that Stage 2 demolition will be completed by March-April 2020.
    • The southern podium precast panels have been installed and the structural slabs have been poured to Level 1 in the southern corner of the podium
    • The installation of in-ground services in the basement level are underway.  